Been chewing on this a few weeks now
Instead of buying , modifying & insulating an old pressure vessel ( LP tank or other)
I'm thinking of building an underground tank using ICFs
We've used Owens Corning Fold Form & trained with ARXX ICF's very simple to use, like lego blocks
The OC have 2" of EPS each side of the concrete- my area of choice is wet, so I would probably line the excavation first with a membrane ( EPDM)
Then place some sand for a nice level, consisten base, 2 layers of EPS board and a 6" thick concrete pad with some steel reinforcing ( my days at NCE were not for naught) Then a 6" thick reinforced wall- bathtub if you will fully insulated both sides
Concrete planks for a lid, with more insulation of course
Now i just need to figure out the heat exchangers, piping etc.
OC fold form is a flimsy product- takes a lot of bracing etc. to keep it straight, but in this application true- straight walls are not critical, set up time for a 2000 gallon tank would be about 2 hours- ready for concrete
Any Thoughts on this? I don't want to reinvent the wheel if somebody already worked all of this out- maybe just try & make it a little better.
Chris
Instead of buying , modifying & insulating an old pressure vessel ( LP tank or other)
I'm thinking of building an underground tank using ICFs
We've used Owens Corning Fold Form & trained with ARXX ICF's very simple to use, like lego blocks
The OC have 2" of EPS each side of the concrete- my area of choice is wet, so I would probably line the excavation first with a membrane ( EPDM)
Then place some sand for a nice level, consisten base, 2 layers of EPS board and a 6" thick concrete pad with some steel reinforcing ( my days at NCE were not for naught) Then a 6" thick reinforced wall- bathtub if you will fully insulated both sides
Concrete planks for a lid, with more insulation of course
Now i just need to figure out the heat exchangers, piping etc.
OC fold form is a flimsy product- takes a lot of bracing etc. to keep it straight, but in this application true- straight walls are not critical, set up time for a 2000 gallon tank would be about 2 hours- ready for concrete
Any Thoughts on this? I don't want to reinvent the wheel if somebody already worked all of this out- maybe just try & make it a little better.
Chris