I am trying to get a grip on this.
Here is what I have and plan to do
2= 500 gal lp tanks
supply into the top of both tanks equal length of pipe to charge even
use a 007 pump to pump from the top of both tanks from 2 different pipes to side arm then to forced air heat ex
return from heat ex to bottom of tanks
bottom of tanks to return on wood boiler
Am I over piping this? most of the diagrams show 1 pipe in to tank and a tee to pump then to load but if my pump is running all the time I wouldnt think the tank would charge.
Thanks for your help
Rob
Here is what I have and plan to do
2= 500 gal lp tanks
supply into the top of both tanks equal length of pipe to charge even
use a 007 pump to pump from the top of both tanks from 2 different pipes to side arm then to forced air heat ex
return from heat ex to bottom of tanks
bottom of tanks to return on wood boiler
Am I over piping this? most of the diagrams show 1 pipe in to tank and a tee to pump then to load but if my pump is running all the time I wouldnt think the tank would charge.