Progress report on installation of Englander 30

  • Active since 1995, Hearth.com is THE place on the internet for free information and advice about wood stoves, pellet stoves and other energy saving equipment.

    We strive to provide opinions, articles, discussions and history related to Hearth Products and in a more general sense, energy issues.

    We promote the EFFICIENT, RESPONSIBLE, CLEAN and SAFE use of all fuels, whether renewable or fossil.
  • Super Cedar firestarters 30% discount Use code Hearth2024 Click here
Status
Not open for further replies.

Spoon

Member
Hearth Supporter
Oct 2, 2009
53
Southwest Missouri
Well I got my flue installed. It took longer than I planned. Now I am getting ready to tackle my hearth. The game plan is simple. I am going to remove the carpet. Cut the subfloor. Notch my floor joists. Put the subfloor back down and pour two inches of concrete down. Of course I will have to block up under it. Then I will put tile on it. It actually won't be very expensive. I do have a question for englander owners.

Question 217: Is there an easy way to take off the pedestial and put the legs on? The directions in the manual are cryptic at best. Example it says to lay the stove on its back. The back is the only way I see to access the carriage bolts holding on the pedestial. Any guidance would be appreciated. Thanks.
 
Why pour concrete? 4 layers of 1/2 cement board will do the same and provide a nice, stable, level surface.
 
BeGreen said:
Why pour concrete? 4 layers of 1/2 cement board will do the same and provide a nice, stable, level surface.
Two reasons.
1. The pamplet from the insurance company recommends 2 inches or brick, rock or cement. I really want to keep them happy.
2. The concrete costs $15; the cement board will cost close to $100.
 